dc.description.abstract | An attempt of critical chain method for project consisted of special tasks has been applied.
The probability distribution of such a task duration is discrete, particularly binomial. The sizing of
appropriate path buffer has been suggested. The possibility of early buffer exceeding warning has
been noticed. | pl_PL |
dc.language.iso | pl | pl_PL |
dc.publisher | Wydawnictwo Uniwersytetu Łódzkiego | pl_PL |
dc.relation.ispartofseries | Acta Universitatis Lodziensis, Folia Oeconomica;287 | |
dc.subject | project management | pl_PL |
dc.subject | critical chain | pl_PL |
dc.subject | buffer sizing | pl_PL |
dc.title | Wielkości bufora w metodzie łańcucha krytycznego w przypadkach dwumianowych rozkładów prawdopodobieństwa czasu realizacji zadań | pl_PL |
dc.title.alternative | Buffer Sizing in Critical Chain Method in Case of Binomial Probability Distribution of Task Duration | pl_PL |
dc.type | Article | pl_PL |
dc.page.number | [15]-26 | pl_PL |
dc.contributor.authorAffiliation | Uniwersyt Łódzki, Wydział Zarządzania, Katedra Informatyki | pl_PL |
dc.references | Ashtiani B., Jalali G.-R., Aryanezhad M.B., Makui A. (2007), A New Approach for Buffer Sizing in Critical Chain Scheduling, Proceedings of the 37th International Conference on Computers and Industrial Engineering, October 20–23, 2007, Alexandria, Egypt, edited by M. H. Elwany, A. B. Eltawil | pl_PL |
dc.references | Geekie A., Steyn H. (2008), Buffer Sizing for the Critical Chain Project Management Method, „South African Journal of Industrial Engineering”, Vol. 19(1) | pl_PL |
dc.references | Goldratt E.M. (2009), Łańcuch krytyczny: projekty na czas. Wydawnictwo Mint | pl_PL |
dc.references | Kuchta D. (2004), The Critical Chain Method In Project Management – a Formal Description, „Badania Operacyjne i Decyzje”, nr 1 | pl_PL |
dc.references | Mansoorzadeh S., Yusof S. M. (2012), Risk Based Schedule Reliability in Construction Phases of EPC Projects in Power Industry, Proceedings of the Asia Pacific Industrial Engineering & Management Systems Conference | pl_PL |
dc.references | Połoński M., Pruszyński K. (2008), Lokalizacja buforów czasu w metodzie łańcucha krytycznego w harmonogramach robót budowlanych, „Przegląd Budowlany”, nr 2 i 3 | pl_PL |
dc.references | Rasmy M.H., Abdelsalam H.M., Hussein R.R. (2007), A Simulation Approach for Determining Buffers’ Sizes in Critical Chain Project Networks, Proceedings of the 37th International Conference on Computers and Industrial Engineering, October 20–23, 2007, Alexandria, Egypt | pl_PL |
dc.references | Razaque A., Bach Ch., Salama N., Alotaibi A. (2012), Fostering Project Scheduling and Controlling Risk Management, „International Journal of Business and Social Science”, Vol. 3, No. 14 [Special Issue – July 2012] | pl_PL |
dc.references | Tian W., Demeulemeester E. (2010), Railway Scheduling Reduces the Expected Project Makespan, Katholieke Universiteit Leuven KBI 1004. Available at SSRN: http://ssrn.com/abstract= 1551262 or http://dx.doi.org/10.2139/ssrn.1551262 | pl_PL |
dc.references | Zhang M., Chen R. (2008), An Investigation of Time Buffer into the Fundamentals of Critical Chain Project Management: A Behavioral Perspective, POMS 19th Annual Conference La Jolla, California, U.S.A. May 9 to May 12 | pl_PL |