Koncepcja systemu harmonogramowania montażu budynków dla Łódzkiego Kombinatu Budowy Domów w oparciu o standardowe pakiety ICL NIMMS
Streszczenie
Introduction of standard programmes, allowing for big savings
of money, work, and time in introduction in information
systems, largely facilitated the work of users of digital
computers. Another modern information tool, enjoying a growing
popularity recently, is the system of data base management. At
present there are available and successfully used (due to compatibility
of ICL-1900 and 0dra-1300 systems) propositions of
the ICL company, and especially the NIMMS system and data base
management system DSM-2. The article discusses the possibility and
advisability of employing two NIMMS packages by the Housing
Construction Company in Łódź. These are Requirements Planning
and POWER packages. The Requirements Planning package, on the basis
of material plan of buildings assembly along with construction
completion time and warehouse information about* stocks
level, defines real demand for production of component elements
of buildings and for purchase of materials necessary
for securing production requirements. The POWER package performs
balancing of production plan and production capacity of machinery
and equipment by means of PERT network and provides
a feasible time scheduling for site assembly. NIMMS system
packages are especially valuable for those companies which must
tackle the problem of multi-stage assembly control, and the above
mentioned Housing Construction Company is among those companies.
Moreover, the user employing DMS-2 can easily and quickly
expand possibilities of the NIMMS System having an easy
access to its information resources.